Planning
By selecting the option
to apply an action, MRP will determine how to resolve the shortage
issue. It will blow through the Bill Of Materials (BOM) to schedule
purchases of raw materials, and/or to schedule manufacturing orders
for sub-assemblies. The action is then displayed on the screen, in
the proper time bucket.
The action is only a
suggestion. The user can then add or edit the system-developed
suggestion manually, and then firm it up. In the case of a purchased
part, System 2000 will allow the user to create the purchase order
using min/max, EOQ, or the actual MRP suggestion. In the case of a
manufactured part, System 2000 will allow the user to create the
manufacturing order using either the MRP recommended quantity or the
manufacturing lot size.
**Please
note that in System 2000's MRP, the user can generate a purchase
order for a manufactured item.
Users also have the
ability to view orders that are deemed to be in a status of
critical, expedite, and delay. Through the setup of MRP, the user
can define time periods as to when orders will meet these criteria.
Users can then choose to select only those orders in a given status
and take appropriate action.
What MRP Does
MRP is a tool to help
manage production and purchasing management. MRP assumes that there
is sufficient capacity to produce the suggestions put forth.
Although MRP is a common
term, no two MRP systems look and plan in the same ways. The
differences may include the underlying logic, the user interface,
and the phrases or jargon used, etc. The purpose of this document is
to outline how System 2000's MRP operates, and the data used to
develop the plan. In order to fully utilize MRP, several other
modules of System 2000 are required to be installed, and
operational. These modules include Customer Orders, Purchasing,
Inventory Management, Sales Analysis, and Manufacturing Orders.
Every effort has been
made to clearly explain the components of demand and operations of
System 2000's MRP. Please refer to the appropriate documentation for
more details on any of the points discussed in this white paper.
MRP Has Three Basic
Steps:
-
Identifying
Requirements For Items To Be Included In An MRP Run
-
Running MRP - Creating
The Suggestions
-
Firming The Suggestions
To Release MO's And PO's
Step I: Identifying
Requirements
MRP plans the purchasing
and manufacturing of products. Careful attention must be made to the
accuracy and completeness of the data. For example, System 2000 will
allow the user to purchase an item coded as manufactured. In order
to achieve this result, the preferred vendor must be entered in the
item balance file. Further, MRP is company and location sensitive so
all data must be accurate in order for MRP to be truly effective.
Elements such as out dated bills of material, and lead times can
negatively impact the results of MRP.
MRP looks at several
components of demand in order to create its suggestions. The
requirements include:
-
Quantity On Hand
-
Quantity On Open
Purchase Order
-
Quantity In / Or
Planned For Manufacturing
-
Quantity Committed To
Existing Orders
-
Quantity Forecasted
MRP is highly date
sensitive. As such, it is important to understand the dates used in
running MRP. The quantity on open Purchase Orders uses the line item
due date for MRP purposes, the quantity in or planned for
manufacturing uses the Manufacturing Order due date, and the
quantity committed uses the requested ship date from the customer
order. The forecasted quantity is populated from the selected
forecast schedule that was created in Sales Analysis. Please note
that MRP does not require forecasting in order to run.
In planned manufacturing
orders, a Manufacturing Order type of 'P' is entered in much the
same way as a made-to-stock order, and will be included in an MRP
run. It is critical that the proper due date be entered when
creating the planned Manufacturing Order.
For an item coded as an
'M' or 'K', System 2000 will blow through the Finished Assemblies
file, determine which items will be effected, and create suggestions
for those components as well.
For items coded as 'C'
for configured, System 2000 only plans for this item type when a
Customer or Manufacturing Order has been created and the features
and options selected. Please refer to the System 2000 documentation
for more details on Item Configuration.
MRP generation may be
done at any time, and then analyzed on the screen, or in a report
(see samples below). Both the on-screen inquiry, and the report,
allow the user to determine which items are considered 'critical',
'expedite', or 'delay' based on the user-defined parameters. As part
of the end of day routine, MRP will be run automatically.
MRP may be run for one
plant, one item, only items being coded as 'critical', 'expedite',
or 'delay', etc. The parameters for defining these statuses are
user-defined.
Step II: Running MRP -
Creating The Suggestions
MRP will be run as part
of the end of day routine to identify items as 'critical',
'expedite', or 'delay', but the user may also select to run the full
MRP at any time by selecting the MRP Report program. MRP suggestions
may be viewed on a daily, weekly, or monthly basis directly on the
screen. The user can dynamically change the planning horizon while
in MRP. MRP will highlight where shortages exist allowing the user
to drill down to any of the factors effecting the MRP run for
greater details including expected receipt dates, and customer
orders making up the demand.
Once the apply action
option is selected, MRP will blow through the Finished Assembly file
for a given 'K' 'M' or 'C' item with open demand, select the
effective components, and suggest the manufacturing / purchasing of
the components. At this point in the MRP process, this is a
suggestion only. The date bucket into which MRP will suggest the
purchase / manufacture of a product will take into account all lead
times found in the item balance file.
Step III: Firming The
Suggestions To Release MO's And PO's
MRP then allows the user
to override the MRP suggestion in a number of ways. The user can
manually override the quantity and vendor, or use the batch size
found in the item balance file. The user may also opt to simply
accept the MRP suggestion and create a Manufacturing Order /
Purchase Order.
Once accepted, Purchase
Orders can be reviewed and released. Once completed, the Purchase
Order may be faxed, printed, and/or e-mailed to the vendor based on
the settings in the Vendor Master File.
Manufacturing Orders are
then created including the appropriate lead-time offsets, and the
components allocated or ordered. The production schedule will be
affected and manufacturing scheduling will be alerted through the
Production Scheduling system. |